Tutorial Step 15: Set the Baseline
When you have a schedule set up and balanced properly, and the project is ready to begin, choose Set Baseline from the Project menu. This copies the schedule you created into the baseline schedule or schedules. The baseline schedules remain unchanged as you update the actual schedule; as the project goes on you can keep track of how closely it is following the original plans.